City of Georgetown, Texas
City Facilities

San Gabriel Wastewater Treatment Plant Improvements

Share

December 14th, 2008 by Webmaster

Location
1107 North College Street

Traffic Impacts
No traffic impacts

Duration

July 2008 - September 2009

Current Status

 Project is complete and in service.

Scope
This project will consists of new headworks with fine screen, wet weather basin for peak storage, pump station for wet weather flows, and new force main.

Cost
$3,564,878.00

Contractor Excel Construction

Contact
Michael Hallmark
Project Manager
Systems Engineering
Office:512-930-3569
Mhallmark@georgetowntx.org