City of Georgetown, Texas
City Facilities

LWTP 3 MG Clearwell

Share

December 11th, 2008 by Webmaster

Location
3601 D B Woods

Traffic Impacts
No impact on traffic

Duration November 2009 – August 2010

Current Status  Pre-Con scheduled for November 11,2009 at 1:30 PM.

 Cost $2,622,800.00

Scope
This project consists of constructing a 3-million gallon Clearwell.

Contractor  CCI

Contact
Michael Hallmark
Project Manager
Systems Engineering
Office:512-930-3569
Mhallmark@georgetowntx.org


Posted in Water



Print This Post Print This Post