Location
3601 D B Woods
Traffic Impacts
No impact on traffic
Duration November 2009 – August 2010
Current Status Pre-Con scheduled for November 11,2009 at 1:30 PM.
Cost $2,622,800.00
Scope
This project consists of constructing a 3-million gallon Clearwell.
Contractor CCI
Contact
Michael Hallmark
Project Manager
Systems Engineering
Office:512-930-3569
Mhallmark@georgetowntx.org