City of Georgetown, Texas
City Facilities

Construction Updates

Oak Tree Bridge

September 15th, 2009 by Webmaster

Oak Tree Bridge:  Bridge Deck concrete placement complete. Bridge rail construction completed end of October. Painting of the rails to begin in November, with approach slab and road work scheduled for completion end of December.
All scheduling information given is weather-permitting. If you have any questions, please contact Joel Weaver, project manager, at (512) 948-1300.
 
 

Read more...

Posted in Streets | 2 Comments »

Williams Drive Widening Project

July 24th, 2009 by Keith Hutchinson

Resources

Construction Updates
Williamson County Road Bond Site

Update, September 4, 2009 from PBS&J:  No work will be performed on the project on Monday, September 7 due to Labor Day holiday. Asphalt overlay work will resume after the holiday and continue until approximately September 16. One lane of traffic will be maintained in each direction during this operation. [...]

Read more...

Posted in Williams Drive | 20 Comments »

College St. Bridge – Photos!

July 23rd, 2009 by Webmaster

College Street Bridge:  The final section of bridge deck is scheduled for placement in November. Construction of the traffic circle will begin the week of November 9th, with a detour to be in place until the bridge is open.

Read more...

Posted in Streets | 1 Comment »

College Street Bridge Construction

July 13th, 2009 by Keith Hutchinson

11-9-09 College Street Bridge:  The final section of bridge deck is scheduled for placement in November. Construction of the traffic circle will begin the week of November 9th, with a detour to be in place until the bridge is open.
The low-water crossing on Morrow Street and other sections of Morrow Street will remain open during [...]

Read more...

Posted in Streets | 9 Comments »

Rock Street WW Extension & Pedestrian Bridge

May 6th, 2009 by michael hallmark

Location: Rock Street from 3rd to the North San Gabriel River.
Traffic Impacts: Rock Street from Blue Hole Park to Third Street will be closed. The hike and bike trail will be closed  from Austin Ave to Blue Hole Park. The Park will be open. 

Duration:From Summer of 2009 to Spring of 2010
Scope: This project will consists [...]

Read more...

Posted in Blue Hole, Water | No Comments »

Oak Tree Drive Crossing Closes on April 21

April 16th, 2009 by Keith Hutchinson

The low-water crossing over Berry Creek on Oak Tree Drive will be closed starting on Tuesday, April 21. The closure is to allow for the construction of the new Oak Tree Drive Bridge. According to the construction timeline, the new bridge should be complete and open to traffic by January 2010, weather permitting.
During the construction [...]

Read more...

Posted in Streets | 2 Comments »

Oak Tree Drive Bridge Construction to Begin

February 18th, 2009 by Keith Hutchinson

Construction on the new bridge over Berry Creek on Oak Tree Drive is expected to begin in March and will be completed and opened for traffic in 10 months, weather permitting. During the construction period, the crossing over Berry Creek at Oak Tree Drive will be closed.
At the February 10 meeting, the city council approved [...]

Read more...

Posted in Streets, Water | 2 Comments »

Recreation Center: Jan. photos

January 17th, 2009 by Keith Hutchinson

Final preparations are being completed on the new Recreation Center addition for the Grand Opening on Saturday, January 31. Ceremonies start at 10 a.m. followed by facility tours and demonstrations in new recreation areas. Regular use of the facility begins on Monday, February 2.
Below are photos taken on January 8, 2009.
The exterior of the new [...]

Read more...

Posted in Rec Center | 7 Comments »

Rec Center update, Dec. 11

December 29th, 2008 by Keith Hutchinson

The Grand Opening of the new Recreation Center is scheduled for Saturday, January 31. Ceremonies start at 10 a.m. followed by facility tours and demonstrations. Regular use of the facility begins on Monday, February 2.
Below are construction photos of the new Recreation Center taken on December 11, 2008.
Recreation Center Supervisor Greg Olmer and Recreation Specialist [...]

Read more...

Posted in Rec Center | 9 Comments »

San Gabriel Wastewater Treatment Plant Improvements

December 14th, 2008 by Webmaster

Location
1107 North College Street
Traffic Impacts
No traffic impacts
Duration
July 2008 - September 2009
Current Status
 Project is complete and in service.
Scope
This project will consists of new headworks with fine screen, wet weather basin for peak storage, pump station for wet weather flows, and new force main.
Cost
$3,564,878.00
Contractor Excel Construction
Contact
Michael Hallmark
Project Manager
Systems Engineering
Office:512-930-3569
Mhallmark@georgetowntx.org

Installing 24″ line near Wet Weather Basin

Read more...

Posted in Water | No Comments »

Only show stories about: