Construction Updates
San Gabriel Wastewater Treatment Plant Secondary Containment 3BQ
Location: 1107 North College Duration: December 2011 to June 2012 Contractor: CCA Current Status: Containment strucure is complete Engineer: KPA Contact: Michael Hallmark Project Manager Office: 512-930-3569 Michael.hallmark@georgetown.org
Read more...Posted in Uncategorized | No Comments »
Lake Water Treatment Plant Expansion Phase III
Location: 3601 DB Woods Duration: February 2010 Summer of 2012 Contractor: CCA Current Status: Clarifiers are complete, new filters are on line belt press is in service. Electrical work and SCADA is on going. Engineer: CDM Contact: Michael Hallmark Project Manager Office: 512-930-3569 Email: Michael.Hallmark@georgetown.org March 2012 January 2012 August 2011
Read more...Posted in Water | No Comments »
FM 971 and NE Inner Loop intersection improvements
Update: Construction on this project started in January 2012. The projected completion is September 2012. The City of Georgetown and Texas Department of Transportation are set to begin interim intersection improvements at the intersection of FM 971 and North East Inner Loop. Sources for project funding are a $343,000 Congressional earmark federal grant and 2008 [...]
Read more...Posted in Streets | No Comments »
Edwards Aquifer Compliance Phase 6-7
Location: Duration: 11/2010 – 8/2011 Scope: This project will consist of pipe bursting and cured-in-place of approximately 20365 LF of 6-inch, 10-inch, 12-inch, and 16-inch wastewater mains. Rehab approximately 50 manholes. Current Status: This project is complete. Cost: 1,183,613.10 Contractor: Fuquay, Inc. and Repipe construction. Contacts: Michael Hallmark Project Manager Office: 512-930-3569 Email: Michael.Hallmark@georgetown.org
Read more...Posted in Uncategorized | No Comments »
Smith Branch Drainage Area Master Plan
The City of Georgetown is currently performing a floodplain study for the Smith Branch watershed. The purpose of this project is to develop a master plan for the Smith Branch Drainage Area. The limits of the study include the West Fork of Smith Branch from upstream of South Austin Avenue to the confluence with the [...]
Read more...Posted in Drainage | No Comments »
Southeast Arterial One
Southeast Arterial One – The project will connect State Highway 130 to Maple Street and Inner Loop by constructing Southeast Arterial One from SH130 to Maple Street and Southwestern Boulevard from Inner Loop to Southeast Arterial One. This project consists of over 20,000 linear feet of roadway improvements that include paving structure, storm water improvements, [...]
Read more...Posted in Streets | 9 Comments »
The Rock Street Extension and Austin Avenue Congestion Mitigation project
The Rock Street Extension and Austin Avenue Congestion Mitigation project will extend Rock Street from Morrow Street South approximately 300 feet. Installation of curb and gutter, paving retaining walls and parking facilities are included. The existing 6-inch water line will be upgraded to 8-inch including all appurtenances. Austin Avenue will be modified by constructing raised [...]
Read more...Posted in Streets | 2 Comments »
LWTP 3 MG Clearwell
Location 3601 D B Woods Traffic Impacts No impact on traffic Duration November 2009 - December 2010 Current Status: In service January 2011 Cost $2,622,800.00 Scope This project consists of constructing a 3-million gallon Clearwell. Contractor CCI Contact Michael Hallmark Project Manager Systems Engineering Office:512-930-3569 Michael.Hallmark@georgetown.org May 6, 2010 October 2010
Read more...Posted in Water | No Comments »
Williams Drive Widening Project
Resources Construction Updates Williamson County Road Bond Site Update from PBS&J, January 14, 2011: Starting Monday, January 17, the Williams Drive road construction contractor will begin work to place the new signal poles and mast arms at the intersections of DB Wood, Wildwood, Woodlake, and Del Webb. Closures of the outside lanes and shoulders will [...]
Read more...Posted in Williams Drive | 39 Comments »
Lake Water Treatment Plant Filter 10
Location: 3601 DB Woods DR. Duration: December 2009 - July 2010 Current Status: Complete Cost: $2,033,200.00 Contractor: CDM Contact: Michael Hallmark Project Manager Office: 512-930-3569 email: Michael.Hallmark@georgetown.org
Read more...Posted in Uncategorized | No Comments »
Only show stories about:

